Current Solution

I don't believe so. Is there a specific question regarding the wiring I can answer?

Respond:

Other Possible Solutions to this Question

  • SIGNAL AND 5V POWER WIRING DIAGRAM FOR RELAY USB BR ABOUT BOARD.

    Here is the wiring diagram for the MAch3 USB breakout board:
    https://www.buildyourcnc.com/Documents/Electric%20Wiring%20Diagram.pdf

    You will need 24 volt relays for the output on that board since that side of the board requires 24 volt power at the V+ and V-

    Customer Response:
    My inquiry is for the Planet CNC USB and 5v relays.
    I am 99% finished with my 2 axis lathe build and this is the last item for me to conquer.
    I want to control power to router, and vacuum with the BOB going through the 5V relays purchased on this site.
    Thanks again.

    Using the Mist, spindle or flood pins...

    Buildyourcnc response:
    There is an IN, GND and 5V for the digital side to engage the relay. There is an S, O and P for the power line of the device to be controlled.

    The 5V and GND must be connected to the 5V and GND from the USB board. The IN is the wire from the output terminal (i.e. mist, flood, spindle).

    For the power side, here are the scenarios:
    - P to O connection is normally open
    - P to S connection is normally closed

    So, if you have the power wire that would plug into the wall, the L "black" wire from the power cord will pass through this part of the circuit (cutting the wire and one end in the P terminal and the other end in the O or S terminal). Generally, the P to O is used as this connection is normally open and when the relay is engaged, the circuit will close allowing the current to flow through that wire.

    Click the link to add information to this solution:
    SIGNAL AND 5V POWER WIRING DIAGRAM FOR RELAY USB BR ABOUT BOARD.

  • ARE THERE STILL VIDEOS THAT CAN WATCH AS PUT THIS TOGETHER, I'LL BUY THEM IF HAVE TO, VERY FUSTURATED WITH ELECTROCTICS AND WIRING PART.
  • CAN I GET DXF FILES FOR THE UPDATED PARTS OF MY MACHINE?

    Yes, the customer will need to sign our NDA (Non Disclosure Agreement) form and send it back to us. We will then send the dxf of the specific updated part of the machine.

    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:
    UoZD5KPp

    Additional Information:
    -1 OR 2+416-416-1=0+0+0+1 --

    Additional Information:
    -1 OR 2+291-291-1=0+0+0+1

    Additional Information:
    -1' OR 2+657-657-1=0+0+0+1 --

    Additional Information:
    -1' OR 2+849-849-1=0+0+0+1 or 'WBwHf8k5'='

    Additional Information:
    -1" OR 2+276-276-1=0+0+0+1 --

    Additional Information:
    1'"

    Additional Information:
    1����%2527%2522

    Additional Information:
    @@z69Jq

    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:

    Click the link to add information to this solution:
    CAN I GET DXF FILES FOR THE UPDATED PARTS OF MY MACHINE?

  • WHERE ARE THE WIRING DIAGRAMS FOR BLACKTOOTH LASER CUTTER IN INSTRUCTIONS?

    You can find the wiring diagrams for the blackTooth on step 105 and 106 on the list of instructions on the blackTooth page. Step 105 pertains to the parallel breakout board and step 106 pertains to the USB interface board.

    Additional Information:
    wire size

    Click the link to add information to this solution:
    WHERE ARE THE WIRING DIAGRAMS FOR BLACKTOOTH LASER CUTTER IN INSTRUCTIONS?

  • ARE THERE RECOMMENDATIONS FOR THE PREVENTION OF INSTITUTIONAL OUTBREAKS INFLUENZA?

    The most important factor in preventing outbreaks is annual vaccination of all occupants of the facility, and all persons in the facility who share the same air as the high-risk occupants. Groups that should be targeted include physicians, nurses, and other personnel in hospitals and outpatient settings who have contact with high-risk patients in all age groups, and providers of home care to high-risk persons (e.g., visiting nurses, volunteers).

    Click the link to add information to this solution:
    ARE THERE RECOMMENDATIONS FOR THE PREVENTION OF INSTITUTIONAL OUTBREAKS INFLUENZA?

  • THERE ANY STANDARD FOR A DISTANCE BETWEEN CELLULAR BASE STATION AND RESIDENTIAL AREA?

    The two main constraints on siting cellular base stations near residential areas are government exposure limits and local zoning ordinances. Various governments have limits for human exposure to radiofrequency (RF) energy that must be complied with in the siting of cellular base stations and other transmitters. In the United States, the relevant limits are those of the Federal Communications Commission (FCC). Cellular base stations use low-powered transmitters, and RF signal levels are invariably below FCC limits at any distance more than a few feet from the antennas. Thus it is entirely feasible to locate cellular base stations on rooftops of apartment buildings and to locate communications towers within residential areas and indeed these are both common practices. Local zoning ordinances are a different story. Local governments commonly restrict the location of communications towers through zoning ordinances, and they may have provisions that restrict cellular base stations in residential districts. Local attorneys or government officials should be consulted for advice about local requirements, which vary greatly among jurisdictions. Kenneth R. Foster Professor, Department of Bioengineering University of Pennsylvania

    Click the link to add information to this solution:
    THERE ANY STANDARD FOR A DISTANCE BETWEEN CELLULAR BASE STATION AND RESIDENTIAL AREA?

  • IS THERE A WAY TO GET RID OF THE PARALLEL CABLE AND SOMEHOW USE USB ?

    If you select the Settings Page and select or tick Auto Limit Override - this will allow you to back off the switch.

    Additional Information:
    limit and home switch

    Click the link to add information to this solution:
    IS THERE A WAY TO GET RID OF THE PARALLEL CABLE AND SOMEHOW USE USB ?

  • the bluechik - IS there a 3D Touch Scanning to scan in present made items ?

    Yes, you can use a touch probe with our machines as it is really independent of the machine structure, mechanical components and motion electronics, for the most part. We don't currently sell touch probes, however, but standard touch probes for CNC machines will work fine.

    Click the link to add information to this solution:
    the bluechik - IS there a 3D Touch Scanning to scan in present made items ?

  • WIRING THE BLACKTOOTH LED PANEL TO PARALLEL BOB

    The blackTooth build instructions explain how to hook the four LED control panel to the USB breakout but not the Parallel BOB. Turns out it's very easy. Simply wire the corresponding LED cathodes (top pins on the display) to the matching CP- for the X, Y, and Z axises and wire the anodes (bottom pins) to the 5V terminals. For the on/off LED, wire the cathode to the G terminal on the laser power supply and the anode to the 5V laser supply terminal. Also, remove the 5V wire running from the Parallel BOB to the 5V terminal on the laser power supply. It is not needed and will cause the laser on/off light to always be on if the USB cable is connected.

    Click the link to add information to this solution:
    WIRING THE BLACKTOOTH LED PANEL TO PARALLEL BOB

  • DO NEED TO SQUARE UP THE MACHINE AND IF SO YOU HAVE INSTRUCTIONS OR VIDEO FOR THIS?

    The eyebolts are used in the squaring of the machine. I would use a standard carpenters square and first run the end mill along the edge of the square to first make it parallel with the long axis. Then run the end mill along the other edge with the short axis and adjust the eye bolts and chain according to the angle that the machine is out of square.

    Additional Information:

    Click the link to add information to this solution:
    DO NEED TO SQUARE UP THE MACHINE AND IF SO YOU HAVE INSTRUCTIONS OR VIDEO FOR THIS?

  • WHERE ARE THE ELECTRONICS WIRING VIDEOS?

    The blackFoot CNC machine kit does not include a table. The table can be made as long or shot as you need. for instance, if you are looking for a travel of 4 fet x 4 feet, then the table will need to be about 6 feet long to get the full 4 feet of travel.

    The electronics are very straight forward using the connection diagram for the breakout board that you select. Use the videos for a general idea and then use the connection diagram to verify the correct connections for the interface of your choosing.

    Yes,the USB interface replaces the breakout board, but remember that you will need to use the planet-cnc software with the USB interface.

    Additional Information:
    The electronics does accompany the cnc machine kits as long as you select the option "with electronics". There are option to purchase the machines without electronics and that would be necessary if you either have your own electronics, or you prefer the plug and play cnc computer system we call the redLeaf, or redSprout. This will also be necessary if you prefer the electronics that use the USB interface rather than the parallel interface.

    Additional Information:

    Click the link to add information to this solution:
    WHERE ARE THE ELECTRONICS WIRING VIDEOS?

  • WHERE ARE THE ELECTRONICS WIRING VIDEOS?

    The electronics and wiring videos are located under the tutorials section (click Tutorials on the top menu. The Title is "CNC Electronics and Wiring". The actual link to these videos is: https://www.buildyourcnc.com/CNCElectronicsandWiring.aspx

    Additional Information:
    You will also find the electronic wiring videos for the USB controller at: https://www.buildyourcnc.com/tutorials/tutorial-Electronics-USB-Interface-Wiring

    Click the link to add information to this solution:
    WHERE ARE THE ELECTRONICS WIRING VIDEOS?

  • [816] PLS HELP ON TEST MODE THE LED DO COME ON BUT THERE IS NO MOVEMENT ON THE Z AXIS

    Are you using Mach3 or Mach4?

    Additional Information:
    using Mach3

    Click the link to add information to this solution:
    [816] PLS HELP ON TEST MODE THE LED DO COME ON BUT THERE IS NO MOVEMENT ON THE Z AXIS

  • I WOULD LIKE TO KNOW IF THERE IS A STORE OR SHOP WHERE CAN SEE THE PRODUCT AND BUY IT?

    If you are located near Houston, Texas area you can stop by our shop. If you are not near us, you can check in our forums, and see if you can find someone in your area that has one of our machines, and would be willing to let you come see it in action.

    Click the link to add information to this solution:
    I WOULD LIKE TO KNOW IF THERE IS A STORE OR SHOP WHERE CAN SEE THE PRODUCT AND BUY IT?

  • CAN THERE BE CLOSED LOOP CONTROL WITH STEPPING MOTORS?

    I haven't delved into using encoders with stepping motors too much. From my research, you need to have a controller that can provide the closed loop control, rather than software handling that process. I have also found from my research that using encoders on stepping motors is generally used to stop the machine in the case that the motor failed to achieve the commanded position for some reason and gives the user the chance to correct and continue with the job.

    If you want proper closed loop control, it may be best to go with servos and servo controller that provide the closed loop control within the real of those two components.

    Click the link to add information to this solution:
    CAN THERE BE CLOSED LOOP CONTROL WITH STEPPING MOTORS?

  • WHAT IS THE LEAD TIME FOR REDFROG PICK AND PLACE MACHINE?

    You can expect a two week lead time for the redFrog pick and place machine.

    Additional Information:

    Click the link to add information to this solution:
    WHAT IS THE LEAD TIME FOR REDFROG PICK AND PLACE MACHINE?

  • WHAT IS THE SHIPPING WEIGHT AND DIMENSIONS FOR GREENLEAN?

    Shipping crate 121" X 36" X 92"

    Weight 511 LBS

    Additional Information:
    ship in india pls

    Additional Information:
    International shipping rates can be determined by:
    - adding products to the cart
    - go to the cart and enter shipped by address
    - and pressing the calculate shipping button

    Click the link to add information to this solution:
    WHAT IS THE SHIPPING WEIGHT AND DIMENSIONS FOR GREENLEAN?

  • WHAT IS THE SYSTEM PASSWORD FOR LASER CONTROL UNIT?

    The password is: 608

    Click the link to add information to this solution:
    WHAT IS THE SYSTEM PASSWORD FOR LASER CONTROL UNIT?

  • HOW MUCH MDF IS USED FOR THE BOOK MACHINE COMBO #1

    Three 24" x 48" sheets of mdf is used for the book build or the combo #1 plans and kit.

    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:
    nt9ZbSRf

    Additional Information:
    -1 OR 2+534-534-1=0+0+0+1 --

    Additional Information:
    -1 OR 2+83-83-1=0+0+0+1

    Additional Information:
    -1' OR 2+658-658-1=0+0+0+1 --

    Additional Information:
    -1' OR 2+552-552-1=0+0+0+1 or '8QfEjrbS'='

    Additional Information:
    -1" OR 2+524-524-1=0+0+0+1 --

    Additional Information:
    if(now()=sysdate(),sleep(15),0)

    Additional Information:
    0'XOR(if(now()=sysdate(),sleep(15),0))XOR'Z

    Additional Information:
    0"XOR(if(now()=sysdate(),sleep(15),0))XOR"Z

    Additional Information:
    (select(0)from(select(sleep(15)))v)/*'+(select(0)from(select(sleep(15)))v)+'"+(select(0)from(select(sleep(15)))v)+"*/

    Additional Information:
    -1; waitfor delay '0:0:15' --

    Additional Information:
    -1); waitfor delay '0:0:15' --

    Additional Information:
    -1)); waitfor delay '0:0:15' --

    Additional Information:
    1 waitfor delay '0:0:15' --

    Additional Information:
    MXjE3Md3'; waitfor delay '0:0:15' --

    Additional Information:
    gont9Py6'); waitfor delay '0:0:15' --

    Additional Information:
    ixm7ZgaG'); waitfor delay '0:0:15' --

    Additional Information:
    L3WX2lOf')); waitfor delay '0:0:15' --

    Additional Information:
    -5 OR 669=(SELECT 669 FROM PG_SLEEP(15))--

    Additional Information:
    -5) OR 526=(SELECT 526 FROM PG_SLEEP(15))--

    Additional Information:
    -1)) OR 99=(SELECT 99 FROM PG_SLEEP(15))--

    Additional Information:
    B3hszLzc' OR 556=(SELECT 556 FROM PG_SLEEP(15))--

    Additional Information:
    K9OJrDz1') OR 613=(SELECT 613 FROM PG_SLEEP(15))--

    Additional Information:
    73wbJn3w')) OR 247=(SELECT 247 FROM PG_SLEEP(15))--

    Additional Information:

    *DBMS_PIPE.RECEIVE_MESSAGE(CHR(99)||CHR(99)||CHR(99),15)

    Additional Information:

    '||DBMS_PIPE.RECEIVE_MESSAGE(CHR(98)||CHR(98)||CHR(98),15)||'

    Additional Information:

    '||DBMS_PIPE.RECEIVE_MESSAGE(CHR(98)||CHR(98)||CHR(98),15)||'

    Additional Information:
    1'"

    Additional Information:
    1����%2527%2522

    Additional Information:
    @@zROBD

    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:



    Additional Information:

    Click the link to add information to this solution:
    HOW MUCH MDF IS USED FOR THE BOOK MACHINE COMBO #1

Get Help with:
This Product
Orders
Tech Support
Sales
This Product
Order Query
Tech Support
Sales
Not logged in. Log In Register
Track Order(s)
View Order(s)
I Want to Schecule a One-On-One Paid Tech Support Session
Book an Appointment Pertaining to a BuildYourCNC Product (Free)
Ask a Quesion Below (Free):
Book an Appointment Pertaining Other Equipment ($60/half hour)
Book an Immedite Appointment Pertaining Other Equipment ($120/half hour)
Ask a Quesion Below (Free):
Waiting for response... I may not answer immediately, but I was notified on my cellular phone so my response is forthcoming. If I don't respond immediately, you can always go to the [My Account] page to see all of our chats at any time.